Measure L Local Project Benefits

  • Provides $18,528,231 for local streets and road repair and maintenance – more than doubling current funding capacity.
  • Immediate repairs for roads surrounding schools, hospital and the downtown area. Includes $1,852,823 for Safe Routes to Schools and other bike and pedestrian improvements.
  • Provides $1,000,000 for intersection improvements for 108/120 at Rodeo.
    Contributes $59,750,000 towards completion of the North County Corridor (Oakdale Bypass).
  • With the Transportation Sales Tax the City will be able to more than double the number of street projects completed over the next 25 years. In the short term, between 2017 and 2020 the City will be able to repair many of the roadways surrounding the schools, hospital and downtown area.

Click here for a list of Revenues and Expenditures


ExpenditureEffective DateRevenueExpenseTransaction DescriptionDocument Description
OAKDALE STREETS1/10/2018 449,486.75 PAYMENT TO OAKDALE, JUNE 2017-DECEMBER 2017MEASURE L DISTRIBUTION
OAKDALE STREETS2/1/2018 52,110.52 OAKDALE ML18-06, JANUARY 2018 PMT#2OAKDALE ML18-06, JANUARY 2018 PMT#2
OAKDALE STREETS2/28/2018 609,363.15 Pontiac and Lee streets
OAKDALE STREETS3/12/2018 69,480.69 MEASURE L OAKDALE ML18-18, FEBRUARY 2018 PMT #3MEASURE L FEBRUARY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE STREETS3/31/2018 1,505.00 Expenditures
OAKDALE STREETS4/13/2018 3,910.00 MCR ENGINEERING - H STREET PROJECT
OAKDALE STREETS4/24/2018 86,769.47 MEASURE L OAKDALE ML18-27, MARCH 2018 PMT #4MEASURE L MARCH 2018 PAYMENT ALL JURISDICTIONS
OAKDALE STREETS5/11/2018 14,560.00 MCR ENGINEERING - H STREET PROJECT
OAKDALE STREETS5/29/2018 50,102.38 MEASURE L OAKDALE ML18-38, APRIL 2018 PMT #5MEASURE L APRIL 2018 PAYMENT ALL JURISDICTIONS
OAKDALE STREETS6/8/2018 4,643.60 MCR ENGINEERING
OAKDALE STREETS6/14/2018 169,737.43 UNITED PAVEMENT
OAKDALE STREETS6/25/2018 83,793.92 MEASURE L OAKDALE ML18-48, MAY 2018 PAYMENT #6FY17-18 MEASURE L MAY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE STREETS6/30/2018 10,673.00 MCR ENGINEERING
OAKDALE STREETS7/24/2018 61,802.62 MEASURE L OAKDALE ML19-05, JUNE 2018 PMT #1FY18-19 MEAURE L JUNE 2018, PAYMENT #1
OAKDALE STREETS7/31/2018 36,559.47 United Pavement Maintenance InvMagnolia Street
OAKDALE STREETS8/21/2018 67,169.96 MEASURE L OAKDALE ML19-16, JULY 2018 PMT #1FY18-19 MEAURE L JULY 2018, PAYMENT #1
OAKDALE STREETS8/31/2018 351,175.54 United Pavement Management IncMagnolia Street Project
OAKDALE STREETS9/18/2018 60,460.00 MEASURE L OAKDALE ML19-27, AUGUST 2018 PMT #2FY18-19 MEAURE L AUGUST 2018, PAYMENT #2
OAKDALE STREETS9/30/2018 2,505.00 MCR ENGINEERINGH ST
OAKDALE STREETS9/30/2018 8,652.24 MCR ENGINEERINGMAGNOLIA - OAK TO MAXWELL
OAKDALE STREETS9/30/2018 173,931.15 UNITED PAVEMENT MAINTENANCEMAGNOLIA - OAK TO MAXWELL
OAKDALE STREETS9/30/2018533.85SIGNATURE SIGNSMAGNOLIA - OAK TO MAXWELL
OAKDALE STREETS10/24/2018 68,810.06 MEASURE L SEPTEMBER 2018 PAYMENTMEASURE L OAKDALE ML19-38, SEPTEMBER 2018 PMT #3
OAKDALE STREETS11/19/2018 91,268.70 MEASURE L OAKDALE ML19-49, OCTOBER 2018 PMT #4MEASURE L OCTOBER 2018 PAYMENT
OAKDALE STREETS12/19/2018 74,039.58 MEASURE L OAKDALE ML19-60, NOVEMBER 2018 PMT #5MEASURE L NOVEMBER 2018 PAYMENT
OAKDALE STREETS12/31/2018990.00MCR ENGINEERINGCP1814 - H ST - OAK TO ASH
OAKDALE STREETS12/31/2018 1,145.00 MCR ENGINEERINGCP1816 - MAGNOLIA - OAK TO MAXWELL
OAKDALE STREETS12/31/2018 1,259.98 UNITED PAVEMENTCP1809 - THIRD & E
OAKDALE STREETS1/24/2019 74,078.44 MEASURE L OAKDALE ML19-71, DECEMBER 2018 PMT #6MEASURE L DECEMBER 2018 PAYMENT
OAKDALE STREETS2/27/2019 74,314.07 MEASURE L OAKDALE ML19-82, JANUARY 2019 PMT #7MEASURE L JANUARY 2019 PAYMENT
OAKDALE STREETS3/19/2019 76,634.84 MEASURE L OAKDALE ML19-92, FEBRUARY 2019 PMT #8MEASURE L FEBRUARY 2019 PAYMENT
OAKDALE STREETS3/31/2019 1,810.00 MCRcp1814 H St
OAKDALE STREETS3/31/2019160.00Oakdale Leadercp1814 H St
OAKDALE STREETS4/17/2019 71,145.35 MEASURE L OAKDALE ML19-102, MARCH 2019 PMT #9MEASURE L MARCH 2019 PAYMENT
OAKDALE STREETS5/24/2019 73,394.53 MEASURE L OAKDALE ML19-113, APRIL 2019 PMT #10MEASURE L APRIL 2019 PAYMENT
OAKDALE STREETS5/31/2019 3,140.71 azco lightscp1809 - Third & E St
OAKDALE STREETS5/31/2019135.00MCR Engcp1809 - Third & E St
OAKDALE STREETS5/31/2019 1,024.14 Signature Signscp1814- H and Ash
OAKDALE STREETS5/31/2019172.72United Pavingcp1809 - Third & E St
OAKDALE STREETS6/20/2019 58,994.15 MEASURE L OAKDALE ML19-123, MAY 2019 PMT #11MEASURE L MAY 2019 PAYMENT
OAKDALE STREETS6/30/2019376.66MCR ENGINEERINGH ST - OAK TO ASH
OAKDALE STREETS6/30/2019816.66MCR ENGINEERINGH STREET - OAK TO ASH
OAKDALE STREETS6/30/2019 27,500.00 MCR ENGINEERINGPOPLAR ST
OAKDALE STREETS6/30/2019 49,138.85 GEORGE REED CONSTRUCTIONH STREET - OAK TO ASH
OAKDALE STREETS6/30/2019410.00MC ENGINEERINGH ST - OAK TO ASH
OAKDALE STREETS7/23/2019 70,177.97 MEASURE L OAKDALE ML19-133, JUNE 2019 PMT #12FY18/19 MEASURE L PAYMENT; JUNE 2019
OAKDALE STREETS7/31/201945.00MCR ENGIINEERINGPOPLAR AVE
OAKDALE STREETS7/31/2019 3,380.00 MCR ENGINEERINGH STREET OAK TO ASH
OAKDALE STREETS8/28/2019 81,312.26 MEASURE L FY19-20 OAKDALE ML20-05, JULY 2019 PMT #1STANCOG MEASURE L PAYMENT; JUNE 2019
OAKDALE STREETS8/31/2019 24,088.19 United PavementS Fifth Ave - G to J
OAKDALE STREETS9/25/2019 70,485.33 MEASURE L FY19-20 OAKDALE ML20-16, AUGUST 2019 PMT #2STANCOG MEASURE L PAYMENT; AUGUST 2019
OAKDALE STREETS9/30/2019 37,600.46 United Pavement Maintenance IncS Fifth Ave g to J ST
OAKDALE STREETS10/15/2019 101,824.95 United Pavement Maintenance IncS Fifth Ave G to J
OAKDALE STREETS10/31/2019 37,260.76 UNTIED PAVEMENT5TH AVE G TO J
OAKDALE STREETS10/31/2019 51,812.00 GEORGE REEDH ST - OAK TO ASH
OAKDALE STREETS10/31/2019 194,657.83 GEORGE REEDH ST OAK TO ASH
OAKDALE STREETS10/31/2019 2,129.26 MCR ENGINEERING5TH AVE G TO J
OAKDALE STREETS10/31/2019 4,326.67 MCR ENGINEERINGH ST - OAK TO ASH
OAKDALE STREETS10/31/2019520.20SIGNATURE SIGNS5TH AVE - G TO J
OAKDALE STREETS10/31/2019 32,362.69 UNITED PAVEMENT5TH AVE G TO J
OAKDALE STREETS10/31/2019 1,961.09 UNITED PAVEMENT INC5TH AVE G TO J
OAKDALE STREETS11/4/2019 72,192.55 MEASURE L FY19-20 OAKDALE ML20-27, SEPTEMBER 2019 PMT #3STANCOG MEASURE L PAYMENT; SEPTEMBER 2019
OAKDALE STREETS11/21/2019 86,534.05 MEASURE L FY19-20 OAKDALE ML20-38, OCTOBER 2019 PMT #4STANCOG MEASURE L PAYMENT; OCTOBER 2019
OAKDALE STREETS11/30/2019 73,344.35 United PavementSouth 5th St
OAKDALE STREETS12/17/2019 71,652.59 MEASURE L FY19-20 OAKDALE ML20-49, NOVEMBER 2019 PMT #5STANCOG MEASURE L PAYMENT; NOVEMBER 2019
OAKDALE STREETS12/30/2019 274,463.73 United PavementSouth 5th Ave
OAKDALE STREETS12/31/2019 26,906.82 UNited Pavement Maintenance5th Ave
OAKDALE STREETS12/31/2019293.34MCR EngineeringH and Ash St
OAKDALE STREETS12/31/2019 5,259.77 MCR Engineering5th Ave
OAKDALE STREETS1/29/2020 71,292.24 MEASURE L FY19-20 OAKDALE ML20-60, DECEMBER 2019 PMT #6STANCOG MEASURE L PAYMENT; DECEMBER 2019
OAKDALE STREETS1/30/2020 9,455.19 George Reed IncH and Ash St
OAKDALE STREETS1/30/2020 89,795.77 United Pavement Maintenance5th Ave
OAKDALE STREETS1/31/2020742.17Reliance Foundry5th Ave
OAKDALE STREETS1/31/2020 5,505.55 MCR Engineering
OAKDALE STREETS2/24/2020 72,611.47 MEASURE L FY19-20 OAKDALE ML20-71, JANUARY 2020 PMT #7STANCOG MEASURE L PAYMENT; JANUARY 2020
OAKDALE STREETS3/12/2020 96,621.84 MEASURE L FY19-20 OAKDALE ML20-82, FEBRUARY 2020 PMT #8STANCOG MEASURE L PAYMENT; FEBRUARY 2020
OAKDALE STREETS4/28/2020 62,518.63 MEASURE L FY19-20 OAKDALE ML20-93, MARCH 2020 PMT #9STANCOG MEASURE L PAYMENT; MARCH 2020
OAKDALE STREETS5/28/2020 62,626.69 MEASURE L FY19-20 OAKDALE ML20-104, APRIL 2020 PMT #10STANCOG MEASURE L PAYMENT; APRIL 2020
OAKDALE STREETS6/23/2020 55,959.97 MEASURE L FY19-20 OAKDALE ML20-115, MAY 2020 PMT #11STANCOG MEASURE L PAYMENT; MAY 2020
OAKDALE STREETS6/30/2020199.41SAFE T LITE5TH AVE - G TO J
OAKDALE STREETS6/30/2020 7,205.00 MCR ENGINEERINGPOPLAR - LAUREL TO FIRST
OAKDALE STREETS6/30/2020 25,976.32 MCR ENGINEERING5TH AVE G TO J
OAKDALE STREETS6/30/2020 8,775.60 MCR ENGINEERINGH - OAK TO ASH
OAKDALE STREETS6/30/2020741.61George Reed IncH - OAK TO ASH
OAKDALE STREETS6/30/2020 90,604.65 MEASURE L OAKDALE JULY 2020 REVENUE ACCRUALFY19/20 REVENUE ACCRUAL JULY REVENUE
OAKDALE STREETS6/30/2020 60,904.70 MEASURE L OAKDALE JUNE 2020 REVENUEFY19/20 REVENUE
OAKDALE TRAFFIC1/10/2018 89,897.35 PAYMENT TO OAKDALE, JUNE 2017-DECEMBER 2017MEASURE L DISTRIBUTION
OAKDALE TRAFFIC2/1/2018 10,422.10 OAKDALE ML18-06, JANUARY 2018 PMT#2OAKDALE ML18-06, JANUARY 2018 PMT#2
OAKDALE TRAFFIC3/12/2018 13,896.14 MEASURE L OAKDALE ML18-18, FEBRUARY 2018 PMT #3MEASURE L FEBRUARY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE TRAFFIC4/24/2018 17,353.89 MEASURE L OAKDALE ML18-27, MARCH 2018 PMT #4MEASURE L MARCH 2018 PAYMENT ALL JURISDICTIONS
OAKDALE TRAFFIC5/29/2018 10,020.48 MEASURE L OAKDALE ML18-38, APRIL 2018 PMT #5MEASURE L APRIL 2018 PAYMENT ALL JURISDICTIONS
OAKDALE TRAFFIC6/25/2018 16,758.78 MEASURE L OAKDALE ML18-48, MAY 2018 PAYMENT #6FY17-18 MEASURE L MAY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE TRAFFIC7/24/2018 12,360.52 MEASURE L OAKDALE ML19-05, JUNE 2018 PMT #1FY18-19 MEAURE L JUNE 2018, PAYMENT #1
OAKDALE TRAFFIC8/21/2018 13,433.99 MEASURE L OAKDALE ML19-16, JULY 2018 PMT #1FY18-19 MEAURE L JULY 2018, PAYMENT #1
OAKDALE TRAFFIC9/18/2018 12,092.00 MEASURE L OAKDALE ML19-27, AUGUST 2018 PMT #2FY18-19 MEAURE L AUGUST 2018, PAYMENT #2
OAKDALE TRAFFIC10/24/2018 13,762.01 MEASURE L SEPTEMBER 2018 PAYMENTMEASURE L OAKDALE ML19-38, SEPTEMBER 2018 PMT #3
OAKDALE TRAFFIC11/19/2018 18,253.74 MEASURE L OAKDALE ML19-49, OCTOBER 2018 PMT #4MEASURE L OCTOBER 2018 PAYMENT
OAKDALE TRAFFIC12/19/2018 14,807.92 MEASURE L OAKDALE ML19-60, NOVEMBER 2018 PMT #5MEASURE L NOVEMBER 2018 PAYMENT
OAKDALE TRAFFIC1/24/2019 14,815.69 MEASURE L OAKDALE ML19-71, DECEMBER 2018 PMT #6MEASURE L DECEMBER 2018 PAYMENT
OAKDALE TRAFFIC2/27/2019 14,862.81 MEASURE L OAKDALE ML19-82, JANUARY 2019 PMT #7MEASURE L JANUARY 2019 PAYMENT
OAKDALE TRAFFIC3/19/2019 15,326.97 MEASURE L OAKDALE ML19-92, FEBRUARY 2019 PMT #8MEASURE L FEBRUARY 2019 PAYMENT
OAKDALE TRAFFIC4/17/2019 14,229.07 MEASURE L OAKDALE ML19-102, MARCH 2019 PMT #9MEASURE L MARCH 2019 PAYMENT
OAKDALE TRAFFIC5/24/2019 14,678.91 MEASURE L OAKDALE ML19-113, APRIL 2019 PMT #10MEASURE L APRIL 2019 PAYMENT
OAKDALE TRAFFIC6/20/2019 11,798.83 MEASURE L OAKDALE ML19-123, MAY 2019 PMT #11MEASURE L MAY 2019 PAYMENT
OAKDALE TRAFFIC7/23/2019 14,035.59 MEASURE L OAKDALE ML19-133, JUNE 2019 PMT #12FY18/19 MEASURE L PAYMENT; JUNE 2019
OAKDALE TRAFFIC8/28/2019 16,262.45 MEASURE L FY19-20 OAKDALE ML20-05, JULY 2019 PMT #1STANCOG MEASURE L PAYMENT; JUNE 2019
OAKDALE TRAFFIC9/25/2019 14,097.07 MEASURE L FY19-20 OAKDALE ML20-16, AUGUST 2019 PMT #2STANCOG MEASURE L PAYMENT; AUGUST 2019
OAKDALE TRAFFIC11/4/2019 14,438.51 MEASURE L FY19-20 OAKDALE ML20-27, SEPTEMBER 2019 PMT #3STANCOG MEASURE L PAYMENT; SEPTEMBER 2019
OAKDALE TRAFFIC11/21/2019 17,306.81 MEASURE L FY19-20 OAKDALE ML20-38, OCTOBER 2019 PMT #4STANCOG MEASURE L PAYMENT; OCTOBER 2019
OAKDALE TRAFFIC12/17/2019 14,330.52 MEASURE L FY19-20 OAKDALE ML20-49, NOVEMBER 2019 PMT #5STANCOG MEASURE L PAYMENT; NOVEMBER 2019
OAKDALE TRAFFIC1/29/2020 14,258.45 MEASURE L FY19-20 OAKDALE ML20-60, DECEMBER 2019 PMT #6STANCOG MEASURE L PAYMENT; DECEMBER 2019
OAKDALE TRAFFIC2/24/2020 14,522.29 MEASURE L FY19-20 OAKDALE ML20-71, JANUARY 2020 PMT #7STANCOG MEASURE L PAYMENT; JANUARY 2020
OAKDALE TRAFFIC3/12/2020 19,324.37 MEASURE L FY19-20 OAKDALE ML20-82, FEBRUARY 2020 PMT #8STANCOG MEASURE L PAYMENT; FEBRUARY 2020
OAKDALE TRAFFIC4/28/2020 12,503.73 MEASURE L FY19-20 OAKDALE ML20-93, MARCH 2020 PMT #9STANCOG MEASURE L PAYMENT; MARCH 2020
OAKDALE TRAFFIC5/28/2020 12,525.34 MEASURE L FY19-20 OAKDALE ML20-104, APRIL 2020 PMT #10STANCOG MEASURE L PAYMENT; APRIL 2020
OAKDALE TRAFFIC6/23/2020 11,191.99 MEASURE L FY19-20 OAKDALE ML20-115, MAY 2020 PMT #11STANCOG MEASURE L PAYMENT; MAY 2020
OAKDALE TRAFFIC6/30/2020 18,120.92 MEASURE L OAKDALE JULY 2020 REVENUE ACCRUALFY19/20 REVENUE ACCRUAL JULY REVENUE
OAKDALE TRAFFIC6/30/2020 12,180.94 MEASURE L OAKDALE JUNE 2020 REVENUEFY19/20 REVENUE
OAKDALE BIKE1/10/2018 44,948.67 PAYMENT TO OAKDALE, JUNE 2017-DECEMBER 2017MEASURE L DISTRIBUTION
OAKDALE BIKE2/1/2018 5,211.05 OAKDALE ML18-06, JANUARY 2018 PMT#2OAKDALE ML18-06, JANUARY 2018 PMT#2
OAKDALE BIKE2/28/2018 30,553.25 Pontiac and Lee streetsFeb Expenses
OAKDALE BIKE3/12/2018 6,948.07 MEASURE L OAKDALE ML18-18, FEBRUARY 2018 PMT #3MEASURE L FEBRUARY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE BIKE4/24/2018 8,676.95 MEASURE L OAKDALE ML18-27, MARCH 2018 PMT #4MEASURE L MARCH 2018 PAYMENT ALL JURISDICTIONS
OAKDALE BIKE5/29/2018 5,010.24 MEASURE L OAKDALE ML18-38, APRIL 2018 PMT #5MEASURE L APRIL 2018 PAYMENT ALL JURISDICTIONS
OAKDALE BIKE6/25/2018 8,379.39 MEASURE L OAKDALE ML18-48, MAY 2018 PAYMENT #6FY17-18 MEASURE L MAY 2018 PAYMENT ALL JURISDICTIONS
OAKDALE BIKE7/24/2018 6,180.26 MEASURE L OAKDALE ML19-05, JUNE 2018 PMT #1FY18-19 MEAURE L JUNE 2018, PAYMENT #1
OAKDALE BIKE8/21/2018 6,717.00 MEASURE L OAKDALE ML19-16, JULY 2018 PMT #1FY18-19 MEAURE L JULY 2018, PAYMENT #1
OAKDALE BIKE9/18/2018 6,046.00 MEASURE L OAKDALE ML19-27, AUGUST 2018 PMT #2FY18-19 MEAURE L AUGUST 2018, PAYMENT #2
OAKDALE BIKE10/24/2018 6,881.01 MEASURE L SEPTEMBER 2018 PAYMENTMEASURE L OAKDALE ML19-38, SEPTEMBER 2018 PMT #3
OAKDALE BIKE11/19/2018 9,126.87 MEASURE L OAKDALE ML19-49, OCTOBER 2018 PMT #4MEASURE L OCTOBER 2018 PAYMENT
OAKDALE BIKE12/19/2018 7,403.96 MEASURE L OAKDALE ML19-60, NOVEMBER 2018 PMT #5MEASURE L NOVEMBER 2018 PAYMENT
OAKDALE BIKE1/24/2019 7,407.84 MEASURE L OAKDALE ML19-71, DECEMBER 2018 PMT #6MEASURE L DECEMBER 2018 PAYMENT
OAKDALE BIKE2/27/2019 7,431.41 MEASURE L OAKDALE ML19-82, JANUARY 2019 PMT #7MEASURE L JANUARY 2019 PAYMENT
OAKDALE BIKE3/19/2019 7,663.48 MEASURE L OAKDALE ML19-92, FEBRUARY 2019 PMT #8MEASURE L FEBRUARY 2019 PAYMENT
OAKDALE BIKE3/31/2019160.00Oakdale Leadercp1906 Trail
OAKDALE BIKE3/31/2019796.31United Pavementcp1809 Third & E Sidewalk
OAKDALE BIKE3/31/2019406.42United Pavementcp1809 Third &E
OAKDALE BIKE3/31/2019 15,129.89 United Pavementcp1809 Third &E Side Walk
OAKDALE BIKE3/31/2019 7,721.99 United Pavementcp1809 Third &E Sidewalk
OAKDALE BIKE4/17/2019 7,114.55 MEASURE L OAKDALE ML19-102, MARCH 2019 PMT #9MEASURE L MARCH 2019 PAYMENT
OAKDALE BIKE4/30/2019 28,037.06 United Pavement Maintenancecp1809 - Third &E Sidewalk
OAKDALE BIKE4/30/2019 1,475.63 United Pavement Mantenancecp1809 - Third &E sidewalk
OAKDALE BIKE5/24/2019 7,339.47 MEASURE L OAKDALE ML19-113, APRIL 2019 PMT #10MEASURE L APRIL 2019 PAYMENT
OAKDALE BIKE6/20/2019 5,899.43 MEASURE L OAKDALE ML19-123, MAY 2019 PMT #11MEASURE L MAY 2019 PAYMENT
OAKDALE BIKE6/30/2019 4,080.00 MCR ENGINEERINGBRIDLE RIDGE TRAIL
OAKDALE BIKE6/30/2019470.00MCR ENGINEERINGBRIDLE RIDGE TRAIL
OAKDALE BIKE7/23/2019 7,017.82 MEASURE L OAKDALE ML19-133, JUNE 2019 PMT #12FY18/19 MEASURE L PAYMENT; JUNE 2019
OAKDALE BIKE8/28/2019 8,131.23 MEASURE L FY19-20 OAKDALE ML20-05, JULY 2019 PMT #1STANCOG MEASURE L PAYMENT; JUNE 2019
OAKDALE BIKE9/25/2019 7,048.53 MEASURE L FY19-20 OAKDALE ML20-16, AUGUST 2019 PMT #2STANCOG MEASURE L PAYMENT; AUGUST 2019
OAKDALE BIKE11/4/2019 7,219.25 MEASURE L FY19-20 OAKDALE ML20-27, SEPTEMBER 2019 PMT #3STANCOG MEASURE L PAYMENT; SEPTEMBER 2019
OAKDALE BIKE11/21/2019 8,653.41 MEASURE L FY19-20 OAKDALE ML20-38, OCTOBER 2019 PMT #4STANCOG MEASURE L PAYMENT; OCTOBER 2019
OAKDALE BIKE12/17/2019 7,165.26 MEASURE L FY19-20 OAKDALE ML20-49, NOVEMBER 2019 PMT #5STANCOG MEASURE L PAYMENT; NOVEMBER 2019
OAKDALE BIKE1/29/2020 7,129.22 MEASURE L FY19-20 OAKDALE ML20-60, DECEMBER 2019 PMT #6STANCOG MEASURE L PAYMENT; DECEMBER 2019
OAKDALE BIKE2/24/2020 7,261.15 MEASURE L FY19-20 OAKDALE ML20-71, JANUARY 2020 PMT #7STANCOG MEASURE L PAYMENT; JANUARY 2020
OAKDALE BIKE3/12/2020 9,662.18 MEASURE L FY19-20 OAKDALE ML20-82, FEBRUARY 2020 PMT #8STANCOG MEASURE L PAYMENT; FEBRUARY 2020
OAKDALE BIKE4/28/2020 6,251.86 MEASURE L FY19-20 OAKDALE ML20-93, MARCH 2020 PMT #9STANCOG MEASURE L PAYMENT; MARCH 2020
OAKDALE BIKE5/28/2020 6,262.67 MEASURE L FY19-20 OAKDALE ML20-104, APRIL 2020 PMT #10STANCOG MEASURE L PAYMENT; APRIL 2020
OAKDALE BIKE6/23/2020 5,596.00 MEASURE L FY19-20 OAKDALE ML20-115, MAY 2020 PMT #11STANCOG MEASURE L PAYMENT; MAY 2020
OAKDALE BIKE6/30/2020 4,730.00 MCR ENGINEERINGBRIDLE TRAIL
OAKDALE BIKE6/30/2020 9,060.46 MEASURE L OAKDALE JULY 2020 REVENUE ACCRUALFY19/20 REVENUE ACCRUAL JULY REVENUE
OAKDALE BIKE6/30/2020 6,090.47 MEASURE L OAKDALE JUNE 2020 REVENUEFY19/20 REVENUE

Allocations by expenditure categories: